Contract Awarded For Beach Nourishment Work On NC 12 Near Rodanthe

Contract Awarded For Beach Nourishment Work On NC 12 Near Rodanthe

Hi All,For those of you interested in a possible investment property on Hatteras Island but worried about access there is some good news from NCDOT. I came across this article and thought I would share it.

  Tuesday, July 08, 2014
  RALEIGH The U.S. Army Corps of Engineers has awarded a $20.3 million contract to Great Lakes Dredge & Dock Co., LLC of Oak Brook, Ill. for the beach nourishment project north of Rodanthe on Hatteras Island to protect this vulnerable stretch of N.C.12. The Corps of Engineers is administering the contract for the N.C. Department of Transportation.

The contractor will use two dredges to expedite the project, which is expected to be completed around mid-September, weather permitting.

“I want to thank all of the agencies involved in completing the required process to begin this vitally important repair work,” said NCDOT Secretary Tony Tata. “Protecting our coastal roadways through renourishment projects like this one is necessary for the safety of our citizens and visitors, to support our tourism industry and to keep our residents connected to jobs, education and healthcare.”

The project is designed to provide several years of protection before a long-term project is completed for the stretch of N.C. 12 locally known as the “S-Curves” where storms, including Hurricane Sandy, resulted in severe beach erosion along the road in Dare County. Plans include dredging sand from an identified sandbar in the Atlantic Ocean to restore the beach protecting N.C. 12 in the location
shown on this map.

“We offer sincere thanks to Secretary Tata and Governor McCrory for their steadfast support throughout this process,’ said Chairman of the Dare County Board of Commissioners Warren Judge.  “In addition, we thank the men and women of NCDOT for all they do for Dare County each and every day.”

The schedule for the project is very dependent on weather and all work going smoothly. The approximate schedule is as follows:
  • By July 16, preliminary work is expected to be completed and installation of the pipeline from the sand source in the ocean onto the beach begins.
  • The first dredge is scheduled to be on site and working around July 16.
  • The second dredge is currently scheduled to arrive the first week in August and will help accelerate work.
  • The project could be complete by mid-September.
  • Once the project is complete, the contractor will begin de-mobilizing its equipment, which will take several weeks. The Federal Highway Administration approved Hurricane Sandy emergency relief funds to pay for this project.

    While this work is taking place, NCDOT is considering two bridge alternatives as long-term solutions for maintaining access along N.C. 12 to the communities of Hatteras Island. They include a 2.3-mile bridge within the existing easement of N.C. 12, and a 2.6-mile bridge that extends into the Pamlico Sound. NCDOT held public meetings in January in Ocracoke, Rodanthe, Buxton and Manteo to present the two alternatives and gather feedback. The project is in the planning phase, and a preferred alternative is expected to be selected later this summer, with a contract awarded in the fall or early winter of 2014.

    This is the second time the beach nourishment project has been advertised for bids. The project was previously advertised in December 2013. Bids were opened in January; however, only one bid was received due to the large amount of dredging work underway at the time in the northeast, and it was not responsive to the advertisement. Therefore, a contract could not be awarded.

    In addition to this project, NCDOT is also conducting feasibility studies for projects to protect N.C. 12 south of Rodanthe at identified “hot spots” on southern Hatteras Island and Ocracoke Island in Hyde County. The feasibility studies are expected to be complete this fall. More information can be found on the N.C. 12 webpage.

    For more information on NCDOT’s efforts to strengthen N.C. 12 in the Outer Banks, visit the N.C. 12 webpage, “like” the N.C. 12 Facebook page and follow the N.C. 12 Twitter account.

    ***NCDOT***   
                                                                 


Mike Nolan Headshot
Author:
Phone: 252-207-4898
Dated: July 15th 2014
Views: 444
About Mike: Mike is the Broker-in-Charge of Waterfront Properties OBX and has been successfully involved in real...

Property Search









RSS Feed

View our latest blog posts in your RSS reader. Click here to access. RSS

Search Blog

Recent Blogs

Jul 20 2018 3605 1 - The time to buy is NOW !!! Ask me
Dare County NC Flood Maps - https://www.darenc.com/departments
July 30 Wicked Tuna Outer Banks - http://outerbanksvideos.com/wicked
2017 Beach Nourishment Schedules - Projected 2017

Our Bloggers

Saved Properties

This is a list of your favorite properties. We will email you if a property is reduced or leaves the market.

Click 'Save' to add a property to this list.

Register / Login

New & returning visitors please enter your information to login.

By clicking 'register' you are agreeing to our terms of use & giving us expressed written consent to contact you.

Questions? Comments? Complaints?

This message will go directly to the head of our team.

Location & Address

Waterfront Properties OBX
P.O. Box 2059
Kitty Hawk, NC
252-562-9109
252-207-4898